Chelmsford Army and Navy Roundabout: Public Inquiry to Begin Over £81 Million Redevelopment
A public inquiry into land needed for Chelmsford's long-awaited Army and Navy junction redevelopment will begin on Tuesday 24 November, marking another important stage in the £81 million transport project.
Plans to transform one of Chelmsford's busiest and most frequently discussed road junctions are approaching another significant milestone, with a public inquiry scheduled to begin next week.
Essex County Council is seeking approval for compulsory purchase and associated road orders required to deliver the Army and Navy Sustainable Transport Package.
The inquiry will open at 10am on Tuesday 24 November 2026, on the fourth floor of County Hall in Market Road, Chelmsford.
An inspector appointed on behalf of the Secretary of State for Transport will hear objections and representations concerning the orders.
The proposed redevelopment includes replacing the existing Army and Navy roundabout with a new junction layout, expanding Sandon Park and Ride and introducing improvements for buses, pedestrians and cyclists.
Why Is There Another Inquiry Into the Army and Navy?
Although planning permission for the redevelopment was granted in November 2024, the project still requires land and legal rights to carry out the proposed construction work.
Essex County Council has therefore submitted three orders for confirmation:
- An Army and Navy Junction Side Roads Order, covering changes to roads around the junction.
- An Army and Navy Compulsory Purchase Order, covering land and rights required for the junction improvements.
- A Sandon Park and Ride Compulsory Purchase Order, covering land needed for the proposed expansion.
The inquiry will consider objections to these orders and allow relevant parties to present their cases.
It is not a fresh planning application or a vote on whether the existing roundabout should be replaced.
Following the inquiry, the inspector will report to the Secretary of State for Transport, who will decide whether the orders should be confirmed.
What Is Planned for the New Army and Navy Roundabout?
The centrepiece of the redevelopment is a new hamburger roundabout, a design featuring a road running directly through the middle of the junction.
Under the proposals, traffic travelling between Parkway and Essex Yeomanry Way would be able to pass through the centre of the roundabout.
Other movements would continue to use the surrounding junction, with traffic signals controlling vehicle flows.
The design is intended to improve capacity and journey times at a location that regularly experiences severe congestion, particularly during the morning and evening rush hours.
According to Essex County Council, the existing Army and Navy junction is used by up to 75,000 vehicles each day, as well as approximately 72 buses an hour.
The council says the junction already operates beyond its capacity during peak periods, with some journey times exceeding six times their normal duration.
What Else Is Included in the £81 Million Scheme?
The redevelopment involves more than changes to the roundabout itself.
The wider transport package includes improvements designed to make journeys through Chelmsford easier by car, bus, bicycle and on foot.
Proposals include:
- A new road through the centre of the Army and Navy roundabout.
- Improved pedestrian crossings and segregated cycling facilities.
- Replacement of the existing pedestrian subway with ground-level routes.
- A new northbound bus lane on Princes Road.
- Improved bus priority measures on Parkway.
- Expansion of Sandon Park and Ride.
The council hopes these changes will reduce congestion while providing alternatives to driving into the city centre.
The previous Army and Navy flyover, which opened in 1978, was permanently closed in 2019 following concerns about its structural condition.
Its removal left the existing roundabout handling traffic that had previously been able to bypass part of the junction.
Why Are There Objections?
Compulsory purchase powers allow public authorities to acquire land or rights needed for approved projects, subject to legal requirements and confirmation.
However, affected landowners and other eligible parties can object.
According to the council's published case documents, objections have included concerns about land acquisition, environmental mitigation, proposed speed limits and the potential impact on a business car park.
A separate objection relates to land required for the Sandon Park and Ride expansion.
The inquiry will provide an opportunity for unresolved objections to be considered.
Essex County Council has indicated that negotiations with affected landowners can continue alongside the compulsory purchase process.
How Much Will the Army and Navy Redevelopment Cost?
The overall transport package has an estimated cost of approximately £81 million.
The Department for Transport approved an outline business case in October 2023 and agreed to contribute £68.75 million through its Major Road Network programme, subject to conditions.
Essex County Council and Chelmsford City Council are also contributing towards the scheme.
The Government confirmed in July 2025 that the project was among the transport schemes approved to progress following a national spending review.
However, the council must still complete the remaining legal, land acquisition and funding requirements before construction can proceed.
When Will Construction Begin?
The latest published project timetable indicates that construction is scheduled to begin in 2028, with completion expected in 2031.
These dates remain dependent on the necessary approvals, land arrangements and final funding decisions.
The public inquiry does not mean that major construction work is about to begin immediately.
For motorists who use the Army and Navy junction every day, the existing road layout will remain in place while the project moves through its remaining stages.
Can Members of the Public Attend the Inquiry?
The public inquiry is scheduled to begin at:
Date: Tuesday 24 November 2026
Time: 10am
Location: Fourth Floor, County Hall, Market Road, Chelmsford
The inspector will hear representations from remaining objectors and people with an interest in land affected by the compulsory purchase orders.
Other members of the public may be permitted to speak at the inspector's discretion.
The relevant orders, plans and supporting documents are available for inspection at County Hall, Chelmsford Library and Great Baddow Library.
Documents are also available through the Essex Highways website.
What Happens Next?
Following the inquiry, the appointed inspector will consider the evidence and submit a report to the Secretary of State for Transport.
A decision will then be made on whether the compulsory purchase and associated road orders should be confirmed.
The outcome will help determine how the council can proceed with acquiring the land and rights required for the redevelopment.
For Chelmsford residents and commuters, the inquiry represents another important step towards a long-awaited change to one of the city's most congested junctions.
Further information and official documents: https://www.essexhighways.org/highway-schemes-and-developments/army-and-navy-taskforce
Chelmsford City Hub will continue to follow developments as the public inquiry progresses.